Term 1 runs on fresh legs. New plan, new year, everyone's keen, and the first steps of everything get started.
Then Term 2 arrives. The things that started in Term 1 are still running, the next lot are due to begin, and they all land on the same few people. We start carrying things that didn't quite get done. Overwhelm starts to creep in. In our experience that's where a good plan goes quiet.
Nobody announces it. The coaching round slips a fortnight. The community hui moves to "next term". By August the plan is a document again.
Nobody decided to overload anyone
This is the bit we find most useful, because it takes the blame out of it.
Compass Point School is made up, and so is Hannah Zhou, its literacy lead. The hours here are the ones in the demo plan inside Planning Room. Hannah has three hours a week for the plan. She runs the structured literacy programme, which takes three hours a week. Fine. Someone else, in a different meeting, asked her to advise on the assessment audit through Term 2. One hour a week. Also fine.
Each ask was reasonable on its own. Together they're four hours against three, for ten weeks, in the term with the senior camp in it. Nobody made that decision. It happened because nobody added it up.
| Piece of work | Hours a week |
|---|---|
| Runs the structured literacy programme | 3 |
| Advises on the assessment audit | 1 |
| The plan asks | 4 |
| Hannah has | 3 |
Each ask was reasonable on its own. It was the adding up that was missing.
(There's a name for the wider habit. Daniel Kahneman and Amos Tversky called it the planning fallacy - we tend to underestimate what a piece of work will take, even when we've been caught out before. Daniel Kahneman writes about it in Thinking, Fast and Slow.)
Why May is the expensive month to find out
By May the term is under way, the person is already tired, and most of the choices have gone. What's left is pushing through or quietly dropping something, and neither of those is a decision anyone gets to feel good about. We keep thinking we can catch up....but we never do.
In November nothing has started, so moving an initiative to another term, sharing it or dropping it costs nobody anything. By May every one of those moves has a price.
What we'd do in November
First, lay every initiative across the four terms on one page and look for the term where the most things overlap. It's usually obvious once it's drawn.
Second, for the three to five people whose names appear most, add up the hours each term asks of them against the hours they really have. (That's the twenty-minute check, and there's a one-page worksheet for it.)
Third, make the moves while they're cheap. Move the work to a lighter term, share it, add cover, or take something out.
Fourth, write down what came off. Work that was dropped without being written down has a way of creeping back in March.
Last, put a date in Term 1 to look again. A plan that fitted in November can stop fitting the day someone goes on leave.
What moves at Compass Point
The demo plan leaves Hannah's clash in on purpose, so there's something to find. The fix is one move. The assessment advice goes to Term 4, after the literacy programme wraps up. Hannah's Term 2 goes back to three hours against three. Camp week is still tight, and the board knows that, because it's written down.
It takes one conversation. The same conversation in May would be about a tired person and a late programme.
What would your Term 2 look like, laid out on one page?