In our experience a plan gets checked for money long before anyone checks it for hours. The budget has a line for everything. We never budget and measure people's time.
Here's a check that needs a pen, the annual plan and about twenty minutes. No software. (We make software that does this, and we'd still start with the pen.)
Three numbers for each person
That's the whole check. The hours a person really has for plan work in a week. The hours the plan asks of them. And the gap between the two.
It's plain arithmetic, the kind anyone could do on the back of the board papers. What makes it useful is that it rarely gets done.
Start with the names
We'd go through the plan and put a tick beside a name every time it appears next to an action. Then we'd pick the three to five people with the most ticks. They're the ones worth twenty minutes.
(If one of those names is yours, that's worth noticing too.)
The hours a person really has
This is the honest bit, and it works far better done with the person than about them.
It starts with their working week. Then everything that's already spoken for comes off - teaching, duty, meetings, covering a class when there's no reliever, the regular stuff that happens whether there's a plan or not. What's left is what they've got for the plan in an ordinary week.
Then one more question. How many weeks in the term are actually ordinary? Report-writing weeks, camp, production week..... those weeks give the plan nothing.
What the plan asks
For every piece of work with their name on it, a rough guess at hours a week, and which weeks it runs. Rough is fine. Being an hour out won't change the answer. Being a whole person out will.
A worked example
Compass Point School is made up, and so is everyone in it. The hours and weeks here are the ones in the demo plan inside Planning Room.
Hannah Zhou is the literacy lead. The demo plan gives her three hours a week for the plan. It doesn't say how that three was worked out, so say her working week is forty hours, and thirty-seven of them are spoken for.
The plan has her name on two things. Running the structured literacy programme, at three hours a week from the start of Term 1 to the end of Term 3. And advice on the assessment audit, at one hour a week through Term 2.
So Term 2 asks for four hours a week, and Hannah has three. One hour over. Doesn't sound like much.
Now the ordinary-weeks question. Term 2 at Compass Point runs for ten weeks, and in week three the senior camp takes Hannah away. So Hannah really has three hours in each of nine weeks, which is 27 hours. The plan asks for four hours in each of ten weeks, which is 40. The gap is 13 hours, in the term with more plan work in it than any other.
| Hours a week | Weeks | Hours in the term | |
|---|---|---|---|
| The hours she really has | 3 | 9 | 27 |
| The hours the plan asks | 4 | 10 | 40 |
| The gap | 13 short |
One hour over doesn't sound like much. Thirteen hours short, in the busiest term of the year, sounds like May.
What to do with the answer
There are only four moves. Move the work to a lighter term. Share it with someone who has room. Add cover so the hours exist. Or take something out of the year.
The demo plan leaves Hannah's clash in on purpose, so there's something to find. The move at Compass Point is to shift the assessment advice to Term 4, when the literacy programme has wrapped up and Hannah has room. Term 2 goes back to three hours a week against three. Camp week is still a squeeze. The difference is that everyone knows it in November.
The decision still belongs to the people who own the plan. The check means it gets made early.... and not in May, by whoever runs out of puff first.
Whose name has the most ticks in your plan?
There's a one-page worksheet for this check. It's free, and there's no form to fill in. Get the capacity check